construction process
|
07 November -2024 |
Aluminum stained glass windows
Plastering works and plastering of the entrance hall have been completed. Installation of Alucobond and travertine cladding are underway on the external facade. Plastering of the apartments on the 2nd floor is underway. Aluminum stained glass windows have been installed on the 9th floor and above. Central wiring of the building has begun: sewage, ventilation, water. |
Gallery
|
Gallery |
|
|
|
28 October -2024 |
Neighborhood partitions
Removal of neighborhood partitions and sand-cement plastering was completed. Ventilation and water-sewerage are being connected. On the 7th floor, the hall is plastered with isogypsum. The facade, including the 9th floor, was covered with travertine stone and stained glass windows. |
Gallery
|
Gallery |
|
|
|
04 October -2024 |
Internal works
Balconies have been finished. Alukabond was applied to the facade. - On the 1st floor (-3.20 mark) a self-leveling floor was laid. Up to the 8th floor, block piling works of neighborhood walls have been completed. Travertine stone was laid on the facade including the 10th floor. Including the 11th floor, aluminum stained glass windows were installed. |
Gallery
|
Gallery |
|
|
|
08 August -2024 |
12th floor
The roof tile of the 12th floor (+35.28 mark) was poured. Up to the 8th floor, block piling works of neighborhood walls have been completed. Travertine stone was laid on the facade including the 4th floor. Including the 5th floor, aluminum stained glass was inserted and Alucobond was attached. |
Gallery
|
Gallery |
|
|
|
27 May -2024 |
11th floor
The tile of the 11th floor is completed in Bagebi. |
Gallery
|
Gallery |
|
|
|
20 May -2024 |
10th-floor columns
Including the 9th floor, the monolith works have been completed. On the 10th floor, columns, and beams are poured, and reinforcement is mined (rebar burning). Up to the 6th floor, the construction of the inner walls of the apartments is in progress. |
Gallery
|
Gallery |
|
|
|
25 April -2024 |
Monolith works
At the +18.98 mark in Bagebi, the work on the monolith of the residential floor has been completed and the columns of the 8th floor are being reinforced (rebar burning). |
Gallery
|
Gallery |
|
|
|
03 April -2024 |
6th floor
Columns and rails have been poured on the 5th floor, while iron work is being done on the 6th floor. |
Gallery
|
Gallery |
|
|
|
08 March -2024 |
5th floor
At the +12.58 mark, preparatory works for the columns of the 5th floor are in progress. |
Gallery
|
Gallery |
|
|
|
23 February -2024 |
Columns
From the first to the 5th floor, the monolith work was completed, and the support columns were arranged on the 6th floor. |
Gallery
|
Gallery |
|
|
|
09 February -2024 |
Construction of convoys
In Bagebi, the columns of the 2nd residential floor are being pulled out at +6.18 mark. |
Gallery
|
Gallery |
|
|
|
26 January -2024 |
2nd residential floor
The construction of the 2nd residential floor at +6.18 mark has started in Bagebi. |
Gallery
|
Gallery |
|
|
|
09 January -2024 |
3rd floor
The removal of the 3rd floor has been completed (+2.98 marks). |
Gallery
|
Gallery |
|
|
|
20 December -2023 |
Column
Preparatory works for the columns of the 3rd floor are in progress. |
Gallery
|
Gallery |
|
|
|
24 July -2023 |
Land works
Land cutting works are in progress. |
Gallery
|
Gallery |
|