01
08 August -2024

12th floor

The roof tile of the 12th floor (+35.28 mark) was poured. Up to the 8th floor, block piling works of neighborhood walls have been completed. Travertine stone was laid on the facade including the 4th floor. Including the 5th floor, aluminum stained glass was inserted and Alucobond was attached.

02
27 May -2024

11th floor

The tile of the 11th floor is completed in Bagebi.

03
20 May -2024

10th-floor columns

Including the 9th floor, the monolith works have been completed. On the 10th floor, columns, and beams are poured, and reinforcement is mined (rebar burning). Up to the 6th floor, the construction of the inner walls of the apartments is in progress.

04
25 April -2024

Monolith works

At the +18.98 mark in Bagebi, the work on the monolith of the residential floor has been completed and the columns of the 8th floor are being reinforced (rebar burning). 

05
03 April -2024

6th floor

Columns and rails have been poured on the 5th floor, while iron work is being done on the 6th floor.

06
08 March -2024

5th floor

At the +12.58 mark, preparatory works for the columns of the 5th floor are in progress.

07
23 February -2024

Columns

From the first to the 5th floor, the monolith work was completed, and the support columns were arranged on the 6th floor.

08
09 February -2024

Construction of convoys

In Bagebi, the columns of the 2nd residential floor are being pulled out at +6.18 mark.

09
26 January -2024

2nd residential floor

The construction of the 2nd residential floor at +6.18 mark has started in Bagebi.

10
09 January -2024

3rd floor

The removal of the 3rd floor has been completed (+2.98 marks).

11
20 December -2023

Column

Preparatory works for the columns of the 3rd floor are in progress.

12
24 July -2023

Land works

Land cutting works are in progress.