construction process
|
21 November -2025 |
Yard area landscaping
Construction work in the project is nearing completion - the entrances have been plastered and painting has been completed. The elevator and stairwell shafts have already been wrapped with aluminum foil. At this stage, the yard area is being cleaned up so that the landscaping work can begin smoothly. |
|
Gallery
|
Gallery |
|
|
05 November -2025 |
Internal works
Elevators have been installed, the installation of elevator frames and buttons has been completed. Marble fixing works are underway. The entrances have been plastered and painting works have been completed. Ceiling painting works are underway. The painting of the railings has been completed in the project. The wrapping of the elevator and stairwell shafts with Alubond is also underway. The installation of communication systems and electricity, water and gas meters has been completed. |
|
Gallery
|
Gallery |
|
|
10 October -2025 |
Stages of internal work
The project is actively undergoing internal work stages that ensure the functionality, safety and comfort of the building. Elevators have been installed and the installation of elevator frames and buttons is underway. The construction of elevator shafts and plastering works have been completed. The installation of the stairwell has been completed, and at this stage the painting of the railings is underway. The entrances have been plastered and security cameras have been installed. Only the painting of the entrance and ceiling remains. The installation of insulating ramps on the roof is beginning, which increases the energy efficiency of the project. |
|
Gallery
|
Gallery |
|
|
26 September -2025 |
Internal works
The works are being carried out according to the planned schedule, in compliance with the highest standards of quality and safety. The installation of elevator frames and buttons is underway, which is an important stage in the completion of the internal infrastructure of the building. The construction of shafts and screeding works has been completed. The railings on the staircase are being painted. In parallel, the installation of fire systems, hoods, and fans is underway, which is an important stage in the improvement of the engineering infrastructure. |
|
Gallery
|
Gallery |
|
|
12 September -2025 |
Railing installation
The installation of railings and fire safety wiring is being completed. Elevator testing and roof plastering are underway. The tiling of balconies and the installation of iron doors to the apartments have been completed. |
|
Gallery
|
Gallery |
|
|
27 August -2025 |
Painting works
The project has completed the laying of stone slabs on the staircase and the installation of railings on the balconies. The installation of the tensioned floor on the roof has been completed and thermal insulation works have begun. The railings on the staircase up to the 7th floor are being attached, and in parallel, the walls of the entrance hall are being painted. |
|
Gallery
|
Gallery |
|
|
11 August -2025 |
Elevator installation works
The suspended floor on the roof has been poured. The installation of the stairwells has been completed. The laying of tiles in the entrance hall of the 6th floor is underway. The installation of one elevator has been completed and the installation of the second elevator has begun. |
|
Gallery
|
Gallery |
|
|
25 July -2025 |
Elevator installation
The staircases on the 10th and 11th floors have been completed. The laying of tiles in the entrance hall has been completed up to the 5th floor. One elevator has already been installed. The installation of glass railings has also been completed. |
|
Gallery
|
Gallery |
|
|
11 July -2025 |
Glass railings
Flooring work is underway on the 11th floor. The laying of tiles in the entrance hall has been completed up to the 4th floor. One elevator has already been installed. 85% of the glass railing installation work has been completed. In parallel, the yard is being arranged - the earth compaction stage has already been completed and landscaping work has begun. |
|
Gallery
|
Gallery |
|
|
25 June -2025 |
Exterior facade
The installation of the stairwells is underway. The laying of tiles in the balconies and entrance hall, including the 4th floor, has been completed. 80% of the installation work on the glass railings has been completed. At the same time, the yard is being improved. |
|
Gallery
|
Gallery |
|
|
10 June -2025 |
Internal works
The installation of apartment doors up to and including the 8th floor has been completed, as well as the installation of stairs and railings in the internal entrance. The work of laying tiles on the balcony and entrance has been completed up to and including the 4th floor. The installation of electrical wiring is underway in the entrance. |
|
Gallery
|
Gallery |
|
|
05 May -2025 |
Internal works
The project has completed the installation of the gas system and the process of plastering the apartments. Meters have already been installed and the wrapping of central gas pipes has begun. Work is underway to lay tiles on the balconies of the 2nd floor and to cover the steps of the stairs with mosaic stone. In parallel, work is underway to tighten the floor on the 3rd and 4th floors. Also, the installation of Alucobond on the back side of the facade. |
|
Gallery
|
Gallery |
|
|
15 April -2025 |
Alucobond installation
The project has completed the installation of railings on the balconies, the installation of ventilation and fire systems, and the installation of a gas system in the apartments. At the same time, the floor screeding works have been completed on the 2nd and 7th floors. Also, the installation of Alucobond on the front side of the facade. In parallel, the floor screeding is underway on the 6th floor, the plastering of the apartments on the 4th and 6th floors, and the plastering and cladding of the entrance walls, including the 4th floor. |
|
Gallery
|
Gallery |
|
|
05 February -2025 |
Balcony railings
The project is completing the removal of internal partitions and gas piping. Work is underway to attach railings to the balconies. |
|
Gallery
|
Gallery |
|
|
27 January -2025 |
Facade works
-Works on laying a tensioned floor are underway on the 1st floor. The removal of internal partitions in the apartments up to the 10th floor has been completed. Gas installation and floor tensioning works in the apartments are underway. 80% of the project's facade works have been completed. |
|
Gallery
|
Gallery |
|
|
07 January -2025 |
Travertine stone
Travertine stone has been installed on the facade and the installation of aluminum stained glass windows has been completed. Plastering of the walls with isogypsum has been completed up to the 7th floor. Installation of alucobond has been completed on the front side of the facade and has begun on the back side. The central wiring of the building has been completed: sewage, ventilation, water. |
|
Gallery
|
Gallery |
|
|
20 December -2024 |
Internal partitions
The front facade is being finished with the application of Alucobond. The interior partitions of the apartment are being removed (60% complete). The elevator installation is also underway. |
|
Gallery
|
Gallery |
|
|
05 December -2024 |
10th floor
The plastering works and the fastening of the Alucobond frame have been completed. Travertine stone has been applied to the facade. Aluminum stained glass windows have been installed up to the 10th floor. The work of removing the interior partitions of the apartment and plastering has begun. The central wiring of the building is underway: sewage, ventilation, water. |
|
Gallery
|
Gallery |
|
|
07 November -2024 |
Aluminum stained glass windows
Plastering works and plastering of the entrance hall have been completed. Installation of Alucobond and travertine cladding are underway on the external facade. Plastering of the apartments on the 2nd floor is underway. Aluminum stained glass windows have been installed on the 9th floor and above. Central wiring of the building has begun: sewage, ventilation, water. |
|
Gallery
|
Gallery |
|
|
28 October -2024 |
Neighborhood partitions
Removal of neighborhood partitions and sand-cement plastering was completed. Ventilation and water-sewerage are being connected. On the 7th floor, the hall is plastered with isogypsum. The facade, including the 9th floor, was covered with travertine stone and stained glass windows. |
|
Gallery
|
Gallery |
|
|
|
04 October -2024 |
Internal works
Balconies have been finished. Alukabond was applied to the facade. - On the 1st floor (-3.20 mark) a self-leveling floor was laid. Up to the 8th floor, block piling works of neighborhood walls have been completed. Travertine stone was laid on the facade including the 10th floor. Including the 11th floor, aluminum stained glass windows were installed. |
|
Gallery
|
Gallery |
|
|
08 August -2024 |
12th floor
The roof tile of the 12th floor (+35.28 mark) was poured. Up to the 8th floor, block piling works of neighborhood walls have been completed. Travertine stone was laid on the facade including the 4th floor. Including the 5th floor, aluminum stained glass was inserted and Alucobond was attached. |
|
Gallery
|
Gallery |
|
|
27 May -2024 |
11th floor
The tile of the 11th floor is completed in Bagebi. |
|
Gallery
|
Gallery |
|
|
20 May -2024 |
10th-floor columns
Including the 9th floor, the monolith works have been completed. On the 10th floor, columns, and beams are poured, and reinforcement is mined (rebar burning). Up to the 6th floor, the construction of the inner walls of the apartments is in progress. |
|
Gallery
|
Gallery |
|
|
25 April -2024 |
Monolith works
At the +18.98 mark in Bagebi, the work on the monolith of the residential floor has been completed and the columns of the 8th floor are being reinforced (rebar burning). |
|
Gallery
|
Gallery |
|
|
03 April -2024 |
6th floor
Columns and rails have been poured on the 5th floor, while iron work is being done on the 6th floor. |
|
Gallery
|
Gallery |
|
|
08 March -2024 |
5th floor
At the +12.58 mark, preparatory works for the columns of the 5th floor are in progress. |
|
Gallery
|
Gallery |
|
|
23 February -2024 |
Columns
From the first to the 5th floor, the monolith work was completed, and the support columns were arranged on the 6th floor. |
|
Gallery
|
Gallery |
|
|
09 February -2024 |
Construction of convoys
In Bagebi, the columns of the 2nd residential floor are being pulled out at +6.18 mark. |
|
Gallery
|
Gallery |
|
|
26 January -2024 |
2nd residential floor
The construction of the 2nd residential floor at +6.18 mark has started in Bagebi. |
|
Gallery
|
Gallery |
|
|
09 January -2024 |
3rd floor
The removal of the 3rd floor has been completed (+2.98 marks). |
|
Gallery
|
Gallery |
|
|
20 December -2023 |
Column
Preparatory works for the columns of the 3rd floor are in progress. |
|
Gallery
|
Gallery |
|
|
24 July -2023 |
Land works
Land cutting works are in progress. |
|
Gallery
|
Gallery |
|