timeline 0 timeline 0 timeline 0 timeline 0
01
21 November -2025

Yard area landscaping

Construction work in the project is nearing completion - the entrances have been plastered and painting has been completed. The elevator and stairwell shafts have already been wrapped with aluminum foil. At this stage, the yard area is being cleaned up so that the landscaping work can begin smoothly. 

Yard area landscaping
timeline 1 timeline 1 timeline 1 timeline 1 timeline 1
02
05 November -2025

Internal works

Elevators have been installed, the installation of elevator frames and buttons has been completed. Marble fixing works are underway. The entrances have been plastered and painting works have been completed. Ceiling painting works are underway. The painting of the railings has been completed in the project. The wrapping of the elevator and stairwell shafts with Alubond is also underway. The installation of communication systems and electricity, water and gas meters has been completed. 

Internal works
timeline 2 timeline 2 timeline 2 timeline 2 timeline 2 timeline 2 timeline 2
03
10 October -2025

Stages of internal work

The project is actively undergoing internal work stages that ensure the functionality, safety and comfort of the building. Elevators have been installed and the installation of elevator frames and buttons is underway. The construction of elevator shafts and plastering works have been completed. The installation of the stairwell has been completed, and at this stage the painting of the railings is underway. The entrances have been plastered and security cameras have been installed. Only the painting of the entrance and ceiling remains. The installation of insulating ramps on the roof is beginning, which increases the energy efficiency of the project.

Stages of internal work
timeline 3 timeline 3 timeline 3 timeline 3 timeline 3 timeline 3 timeline 3 timeline 3 timeline 3
04
26 September -2025

Internal works

The works are being carried out according to the planned schedule, in compliance with the highest standards of quality and safety. The installation of elevator frames and buttons is underway, which is an important stage in the completion of the internal infrastructure of the building. The construction of shafts and screeding works has been completed. The railings on the staircase are being painted. In parallel, the installation of fire systems, hoods, and fans is underway, which is an important stage in the improvement of the engineering infrastructure. 

Internal works
timeline 4 timeline 4 timeline 4 timeline 4 timeline 4 timeline 4 timeline 4
05
12 September -2025

Railing installation

The installation of railings and fire safety wiring is being completed. Elevator testing and roof plastering are underway. The tiling of balconies and the installation of iron doors to the apartments have been completed.

Railing installation
timeline 5 timeline 5 timeline 5 timeline 5 timeline 5 timeline 5 timeline 5 timeline 5
06
27 August -2025

Painting works

The project has completed the laying of stone slabs on the staircase and the installation of railings on the balconies. The installation of the tensioned floor on the roof has been completed and thermal insulation works have begun. The railings on the staircase up to the 7th floor are being attached, and in parallel, the walls of the entrance hall are being painted.

Painting works
timeline 6 timeline 6 timeline 6 timeline 6 timeline 6 timeline 6 timeline 6 timeline 6 timeline 6 timeline 6
07
11 August -2025

Elevator installation works

The suspended floor on the roof has been poured. The installation of the stairwells has been completed. The laying of tiles in the entrance hall of the 6th floor is underway. The installation of one elevator has been completed and the installation of the second elevator has begun.

Elevator installation works
timeline 7 timeline 7 timeline 7
08
25 July -2025

Elevator installation

The staircases on the 10th and 11th floors have been completed. The laying of tiles in the entrance hall has been completed up to the 5th floor. One elevator has already been installed. The installation of glass railings has also been completed. 

Elevator installation
timeline 8 timeline 8 timeline 8 timeline 8 timeline 8
09
11 July -2025

Glass railings

Flooring work is underway on the 11th floor. The laying of tiles in the entrance hall has been completed up to the 4th floor. One elevator has already been installed. 85% of the glass railing installation work has been completed. In parallel, the yard is being arranged - the earth compaction stage has already been completed and landscaping work has begun.

Glass railings
timeline 9 timeline 9 timeline 9 timeline 9 timeline 9
10
25 June -2025

Exterior facade

The installation of the stairwells is underway. The laying of tiles in the balconies and entrance hall, including the 4th floor, has been completed. 80% of the installation work on the glass railings has been completed. At the same time, the yard is being improved.

Exterior facade
timeline 10 timeline 10 timeline 10 timeline 10 timeline 10
11
10 June -2025

Internal works

The installation of apartment doors up to and including the 8th floor has been completed, as well as the installation of stairs and railings in the internal entrance. The work of laying tiles on the balcony and entrance has been completed up to and including the 4th floor. The installation of electrical wiring is underway in the entrance.

Internal works
timeline 11 timeline 11 timeline 11
12
05 May -2025

Internal works

The project has completed the installation of the gas system and the process of plastering the apartments. Meters have already been installed and the wrapping of central gas pipes has begun. Work is underway to lay tiles on the balconies of the 2nd floor and to cover the steps of the stairs with mosaic stone. In parallel, work is underway to tighten the floor on the 3rd and 4th floors. Also, the installation of Alucobond on the back side of the facade.

Internal works
timeline 12 timeline 12 timeline 12
13
15 April -2025

Alucobond installation

The project has completed the installation of railings on the balconies, the installation of ventilation and fire systems, and the installation of a gas system in the apartments. At the same time, the floor screeding works have been completed on the 2nd and 7th floors. Also, the installation of Alucobond on the front side of the facade. In parallel, the floor screeding is underway on the 6th floor, the plastering of the apartments on the 4th and 6th floors, and the plastering and cladding of the entrance walls, including the 4th floor.

Alucobond installation
timeline 13 timeline 13
14
05 February -2025

Balcony railings

The project is completing the removal of internal partitions and gas piping. Work is underway to attach railings to the balconies.

Balcony railings
timeline 14 timeline 14 timeline 14
15
27 January -2025

Facade works

-Works on laying a tensioned floor are underway on the 1st floor. The removal of internal partitions in the apartments up to the 10th floor has been completed. Gas installation and floor tensioning works in the apartments are underway. 80% of the project's facade works have been completed.

Facade works
timeline 15 timeline 15
16
07 January -2025

Travertine stone

Travertine stone has been installed on the facade and the installation of aluminum stained glass windows has been completed. Plastering of the walls with isogypsum has been completed up to the 7th floor. Installation of alucobond has been completed on the front side of the facade and has begun on the back side. The central wiring of the building has been completed: sewage, ventilation, water.

Travertine stone
timeline 16 timeline 16 timeline 16 timeline 16 timeline 16
17
20 December -2024

Internal partitions

The front facade is being finished with the application of Alucobond. The interior partitions of the apartment are being removed (60% complete). The elevator installation is also underway.

Internal partitions
timeline 17 timeline 17 timeline 17 timeline 17 timeline 17 timeline 17
18
05 December -2024

10th floor

The plastering works and the fastening of the Alucobond frame have been completed. Travertine stone has been applied to the facade. Aluminum stained glass windows have been installed up to the 10th floor. The work of removing the interior partitions of the apartment and plastering has begun. The central wiring of the building is underway: sewage, ventilation, water.

10th floor
timeline 18 timeline 18 timeline 18 timeline 18 timeline 18 timeline 18
19
07 November -2024

Aluminum stained glass windows

Plastering works and plastering of the entrance hall have been completed. Installation of Alucobond and travertine cladding are underway on the external facade. Plastering of the apartments on the 2nd floor is underway. Aluminum stained glass windows have been installed on the 9th floor and above. Central wiring of the building has begun: sewage, ventilation, water.

Aluminum stained glass windows
timeline 19
20
28 October -2024

Neighborhood partitions

Removal of neighborhood partitions and sand-cement plastering was completed. Ventilation and water-sewerage are being connected. On the 7th floor, the hall is plastered with isogypsum. The facade, including the 9th floor, was covered with travertine stone and stained glass windows.

Neighborhood partitions
21
04 October -2024

Internal works

Balconies have been finished. Alukabond was applied to the facade. - On the 1st floor (-3.20 mark) a self-leveling floor was laid. Up to the 8th floor, block piling works of neighborhood walls have been completed. Travertine stone was laid on the facade including the 10th floor. Including the 11th floor, aluminum stained glass windows were installed.

Internal works
timeline 21 timeline 21 timeline 21
22
08 August -2024

12th floor

The roof tile of the 12th floor (+35.28 mark) was poured. Up to the 8th floor, block piling works of neighborhood walls have been completed. Travertine stone was laid on the facade including the 4th floor. Including the 5th floor, aluminum stained glass was inserted and Alucobond was attached.

12th floor
timeline 22 timeline 22 timeline 22
23
27 May -2024

11th floor

The tile of the 11th floor is completed in Bagebi.

11th floor
timeline 23 timeline 23 timeline 23 timeline 23
24
20 May -2024

10th-floor columns

Including the 9th floor, the monolith works have been completed. On the 10th floor, columns, and beams are poured, and reinforcement is mined (rebar burning). Up to the 6th floor, the construction of the inner walls of the apartments is in progress.

10th-floor columns
timeline 24 timeline 24 timeline 24
25
25 April -2024

Monolith works

At the +18.98 mark in Bagebi, the work on the monolith of the residential floor has been completed and the columns of the 8th floor are being reinforced (rebar burning). 

Monolith works
timeline 25 timeline 25 timeline 25 timeline 25 timeline 25 timeline 25 timeline 25
26
03 April -2024

6th floor

Columns and rails have been poured on the 5th floor, while iron work is being done on the 6th floor.

6th floor
timeline 26 timeline 26 timeline 26
27
08 March -2024

5th floor

At the +12.58 mark, preparatory works for the columns of the 5th floor are in progress.

5th floor
timeline 27 timeline 27 timeline 27
28
23 February -2024

Columns

From the first to the 5th floor, the monolith work was completed, and the support columns were arranged on the 6th floor.

Columns
timeline 28 timeline 28 timeline 28
29
09 February -2024

Construction of convoys

In Bagebi, the columns of the 2nd residential floor are being pulled out at +6.18 mark.

Construction of convoys
timeline 29 timeline 29 timeline 29
30
26 January -2024

2nd residential floor

The construction of the 2nd residential floor at +6.18 mark has started in Bagebi.

2nd residential floor
timeline 30 timeline 30 timeline 30
31
09 January -2024

3rd floor

The removal of the 3rd floor has been completed (+2.98 marks).

3rd floor
timeline 31 timeline 31
32
20 December -2023

Column

Preparatory works for the columns of the 3rd floor are in progress.

Column
timeline 32 timeline 32 timeline 32
33
24 July -2023

Land works

Land cutting works are in progress.

Land works