01
25 April -2024

Monolith works

At the +18.98 mark in Bagebi, the work on the monolith of the residential floor has been completed and the columns of the 8th floor are being reinforced (rebar burning). 

02
03 April -2024

6th floor

Columns and rails have been poured on the 5th floor, while iron work is being done on the 6th floor.

03
08 March -2024

5th floor

At the +12.58 mark, preparatory works for the columns of the 5th floor are in progress.

04
23 February -2024

Columns

From the first to the 5th floor, the monolith work was completed, and the support columns were arranged on the 6th floor.

05
09 February -2024

Construction of convoys

In Bagebi, the columns of the 2nd residential floor are being pulled out at +6.18 mark.

06
26 January -2024

2nd residential floor

The construction of the 2nd residential floor at +6.18 mark has started in Bagebi.

07
09 January -2024

3rd floor

The removal of the 3rd floor has been completed (+2.98 marks).

08
20 December -2023

Column

Preparatory works for the columns of the 3rd floor are in progress.

09
24 July -2023

Land works

Land cutting works are in progress.